Back to the software solutions

Example site for an entirely fictional business — not a real company.

Inspection RunFairbridge Precision Engineering Inc.

Sample data

Inspection orders

All open orders for the current week — as a list and by stage.

Order, part number or batch
  • Open
  • In-process
  • Incoming goods
  • First article
  • Re-inspection
  • Fails only
  • This week

Inspection orders

OrderPartBatchInspection typeDueSampleInspectorState
PA-2026-1184PartBearing block, 4-way, 41.220-03BatchCH-2026-0771Inspection typeIn-processDue31 JulSamplen = 5InspectorK. OsborneStateAssessment open
PA-2026-1183PartFlange bush, 38.104-01BatchCH-2026-0768Inspection typeIncoming goodsDue31 JulSamplen = 8InspectorM. TurnerStateBeing measured
PA-2026-1181PartCover plate, 52.017-04BatchCH-2026-0765Inspection typeFirst articleDue31 JulSamplen = 3InspectorK. OsborneStateScheduled
PA-2026-1179PartSpacer sleeve, 21.330-02BatchCH-2026-0762Inspection typeIn-processDue31 JulSamplen = 5InspectorR. WilmottStateClosed, pass
PA-2026-1176PartBearing block, 4-way, 41.220-03BatchCH-2026-0759Inspection typeRe-inspectionDue31 JulSamplen = 12InspectorR. WilmottStateFail, batch held
PA-2026-1172PartGuide rail, 47.008-06BatchCH-2026-0754Inspection typeFixture checkDue31 JulSamplen = 1InspectorJ. BeckettStateBeing measured
PA-2026-1168PartClamping piece, 33.451-02BatchCH-2026-0748Inspection typeIn-processDue1 AugSamplen = 5InspectorM. TurnerStateScheduled
PA-2026-1165PartBearing block, 4-way, 41.220-03BatchCH-2026-0742Inspection typeFirst articleDue4 AugSamplen = 3InspectorK. OsborneStateAwaiting customer approval

8 of 18 open inspection orders · filter: current week

By stage

Each card shows order, part and inspector. Dragging changes nothing in this demo.

Scheduled

9 orders
  • PA-2026-1181

    Cover plate 52.017-04 · K. Osborne

    n = 3First article

  • PA-2026-1168

    Clamping piece 33.451-02 · M. Turner

    n = 5In-process

Being measured

6 orders
  • PA-2026-1183

    Flange bush 38.104-01 · M. Turner

    n = 8Incoming

  • PA-2026-1172

    Guide rail 47.008-06 · J. Beckett

    n = 1Fixture

Assessment open

3 orders
  • PA-2026-1184

    Bearing block 41.220-03 · K. Osborne

    1 characteristic failsIn-process

  • PA-2026-1165

    Bearing block 41.220-03 · K. Osborne

    customer approval pendingFirst article

Closed

23 this week
  • PA-2026-1179

    Spacer sleeve 21.330-02 · R. Wilmott

    passIn-process

  • PA-2026-1176

    Bearing block 41.220-03 · R. Wilmott

    fail, batch heldRe-inspection

The project frame

How Awelior would approach this project

Fairbridge Precision Engineering Inc. is invented — the way it is built is not. None of this is work delivered for a client. It is the shape we would give such a project — with the same depth, but without a client who would have to answer for it.

Where it starts

Fairbridge Precision Engineering Inc. inspects in production and documents on paper. Inspection plans live in a spreadsheet, the calibration list is taped to the metrology room door. As long as nothing is challenged that is enough; once a complaint arrives, somebody has to work backwards from the batch through the order to the measurement record — and that path does not exist in a binder.

Decisions

  • Traceability down to the batch as the ground plan

    Inspection order, record, nonconformity and measuring equipment hang on the same chain. That is not one feature among many but the arrangement every other screen follows from.

  • A nonconformity is a case of its own

    A rejection does not end with a red field in the record; it becomes a case with cause, action and effectiveness check. Without that a quality system is a collection of measurements.

  • Measuring equipment with calibration dates in the system

    A caliper whose calibration has lapsed makes every record produced with it contestable. The list on the door knew that too — the record did not.

Deliberately left outNo connection to measuring machines and no statistical process control. Both are the next step and assume the inspection processes are cleanly in the system first — otherwise a control chart gets drawn from values whose origin nobody can evidence.

What is in it

Screens
5
Content blocks
19
Languages
4

Five screens, in all four languages, with sidebar, header and stated role. Navigation works; tables, filters, board, calendar, step chains, history and single records are rendered and inert. Orders, batches and measurements are invented.

How it would go on

  • Instruments and data capture

    Typing measurements in by hand is the most common source of error. Connecting the instruments saves errors rather than time.

  • Standards and audits

    What an auditor wants to see shapes the structure: evidence trails, approvals, document control and the question of who may change what.

  • Connection to production

    Inspection orders arise from production orders. Without that link somebody creates every inspection order by hand — and forgets exactly the ones that matter.

Talk through your project

Sample data

An application like this for your business?

Inspection Run is invented — the way it is cut is not. Applications like this come out of the processes a business already runs.

Sample application by Awelior. Invented business, invented data, nothing stored.